EOSDA Platform Integration Report — Ecological Nest Ltd

Consultancy engagement: prepare EOSDA Platform Integration Report for Ecological Nest Ltd. Involves hosting 4 polygons of areas in the Keta Lagoon Complex Ramsar Site on the EOSDA platform for continuous monitoring. Deliverables include the integration report, platform setup, and full handover with transitional requirements. Contract sum: GHS 150,000. Deadline: 24 April 2026.

Owner: Daniel NsowahClient: Ecological Nest LtdStart: 3 Apr 2026End: 24 Apr 2026

Budget

GHS 150,000

Overall Progress100%
Todo0

Empty

In Progress0

Empty

Review0

Empty

Done25
MEDIUM

Review GIS Farm Management Briefing (2026-05-07)

HIGH

Call Amantin Agro Processing

Overdue · 5 May
CO
MEDIUM

Review GIS Farm Management Briefing (2026-05-01)

Overdue · 5 May
URGENT

Delegate overdue MEA reporting obligations

Overdue · 27 Jun
HIGH

Investigate and Resolve May Finance Anomalies

URGENT

Review GIS module for high-priority farm briefing

URGENT

Address overdue MEA reporting obligations

Overdue · 29 Jun
HIGHM1: Polygon Intake & EOSDA Account Setup

Receive polygon data from Ecological Nest Ltd

Overdue · 4 Apr
DN
HIGHM1: Polygon Intake & EOSDA Account Setup

Validate polygon geometries against Keta Lagoon Ramsar boundary

Overdue · 5 Apr
DN
HIGHM1: Polygon Intake & EOSDA Account Setup

Set up EOSDA platform account and workspace

Overdue · 6 Apr
DN
MEDIUMM1: Polygon Intake & EOSDA Account Setup

Document polygon metadata and baseline characteristics

Overdue · 7 Apr
DN
HIGHM2: Platform Integration & Monitoring Configuration

Upload Polygon 1 to EOSDA and configure monitoring

Overdue · 9 Apr
DN
HIGHM2: Platform Integration & Monitoring Configuration

Upload Polygon 2 to EOSDA and configure monitoring

Overdue · 10 Apr
DN
HIGHM2: Platform Integration & Monitoring Configuration

Upload Polygon 3 to EOSDA and configure monitoring

Overdue · 11 Apr
DN
HIGHM2: Platform Integration & Monitoring Configuration

Upload Polygon 4 to EOSDA and configure monitoring

Overdue · 12 Apr
DN
HIGHM2: Platform Integration & Monitoring Configuration

Capture baseline readings for all 4 polygons

Overdue · 13 Apr
DN
MEDIUMM2: Platform Integration & Monitoring Configuration

Test continuous monitoring alerts and data feeds

Overdue · 14 Apr
DN
HIGHM3: Report Drafting & Quality Review

Draft Report - Introduction and Methodology

Overdue · 15 Apr
DN
HIGHM3: Report Drafting & Quality Review

Draft Report - Polygon Specifications and Baseline

Overdue · 16 Apr
DN
HIGHM3: Report Drafting & Quality Review

Draft Report - Monitoring Config and User Guide

Overdue · 17 Apr
DN
HIGHM3: Report Drafting & Quality Review

Internal quality review of full report

Overdue · 18 Apr
DN
HIGHM4: Handover & Project Close

Prepare handover package

Overdue · 20 Apr
DN
HIGHM4: Handover & Project Close

Draft transitional requirements document

Overdue · 21 Apr
DN
HIGHM4: Handover & Project Close

Handover meeting with Ecological Nest Ltd

Overdue · 23 Apr
DN
HIGHM4: Handover & Project Close

Invoice and project close

Overdue · 24 Apr
DN
Blocked0